You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?
- Risk audits
- Qualitative risk analysis
- Quantitative risk analysis
- Requested changes